Got Plan Review Comments on Your Florida Permit? What They Mean and How to Respond

Nov 5
5 min read

You submitted your permit plans, and the building department sent back a list of comments. It's natural to read that as a rejection. Usually it isn't. Comments are how reviewers tell the applicant what they need to see before they can approve the work, and responding to them is a normal part of permitting in Florida.

What matters is understanding what the comments ask for, how much time you have and how to answer them completely. This guide walks through each of those. If you're still preparing your plans, our guide to what permit plans are explains how the review process works from submission to approval.



Blue rubber stamp on white paper beside a pen, mug, and stack of books on a neat desk.


Comments, Corrections and Denials: What's the Difference?

Building departments use different words in their portals: comments, corrections, deficiencies, "disapproved," "revisions required." The labels vary by jurisdiction. The practical categories are:

  • Completeness notices. Something required for the application is missing, so review can't proceed. Under Florida Statutes s. 553.792, a local government must notify the applicant in writing within 5 business days of receiving an application about any information needed to make it complete.

  • Plan review comments or deficiencies. The application was reviewed, and the reviewer identified items that don't yet show compliance with the code or local requirements. These are the comments most homeowners see.

  • Denial. The application is formally denied. Under s. 553.792, this can happen when a written deficiency notice is not answered with revisions in time (see below).

A comment list, on its own, is not a denial. It is a request for revisions or more information.


How Long You Have to Respond in Florida

This is the part many homeowners don't know. Under s. 553.792, when a local government sends written notice within its review timeframe explaining the reasons an application fails to satisfy the Florida Building Code or local laws, that notice must also state that:

  • the applicant has 10 business days after receiving the notice to submit revisions, and

  • failure to correct the application within 10 business days will result in denial.

If you submit revisions within that window, the statute gives the local agency 10 business days to approve or deny the permit, unless you agree in writing to a longer period.


Two practical takeaways:

  1. Check the date on the notice and count business days right away. Ten business days goes quickly when an engineer or designer needs to revise drawings.

  2. Tell your design team immediately. Don't wait until you've read every comment yourself.

The statute also sets review timeframes for different permit types; for example, 30 business days for residential units under 7,500 square feet reviewed by a local government plans reviewer. Local procedures for extensions and waivers vary, so ask your building department how it handles them. The statute says a local government may not require a waiver of the timeframes as a condition of reviewing an application.


What Plan Review Comments Usually Address

The reasons vary by project, and our permit plans guide covers common problems that can delay approval. In general, comments tend to fall into a few groups:

  • Missing information: a document, calculation or detail the reviewer needs

  • Inconsistencies: a dimension, wall or beam that doesn't match between sheets

  • Code questions: something that doesn't yet show compliance with a specific code section

  • Site and zoning: setbacks, flood elevation or other site requirements

For additions and other structural work, comments often involve the structural drawings. Our guide on when a home addition needs a structural engineer explains what the engineer evaluates and why those sheets get close review.


How to Read and Organize the Comments

Before anyone starts revising, organize what you received:

  1. Download the full comment report and every marked-up sheet. Some portals put comments in one document and markups on the drawings themselves.

  2. Number each comment if the department hasn't, and note which discipline it belongs to: building, structural, zoning, flood, mechanical, electrical, plumbing or fire.

  3. Note the code section cited. Comments often reference a specific code section. That tells your design team exactly what the reviewer is checking.

  4. Flag anything unclear. If a comment can be read two ways, it's better to ask than guess.

  5. Identify who owns each item. Structural comments typically go to the engineer of record; architectural and site comments to the designer; some items may need you to provide a document.


How Design Teams Address Comments

A complete response usually includes three parts:

  • Revised drawings with the changes made, often marked with revision clouds and a revision number or date so the reviewer can find them

  • A response letter or narrative that lists each comment and explains how and where it was addressed, sheet by sheet

  • Supporting documents the comments asked for, such as calculations, product approvals or a survey


The goal is to answer every comment in the same resubmittal. A partial response can lead to another round of comments, which adds time.


If you disagree with a comment, ask your design team to contact the reviewer, cite the code section that applies and explain the reasoning. If that doesn't resolve it, ask the building department about its formal appeal process.


Don't Make Undocumented Changes After Approval

Comments don't stop at approval. If you change the design during construction, the change may need to go back for review. The Florida Building Code's provision on amended construction documents, Section 107.4, as quoted on a Florida building department revision form, states that work must be installed according to the approved construction documents, and that changes not in compliance with them must be resubmitted to the building official for approval as an amended set.


Moving a wall, enlarging an opening or substituting a structural product without approval can create problems at inspection. Talk to your design team before changing anything shown on the approved plans.


What to Prepare When You Discuss Comments With Your Design Team

  • The full comment report and marked-up sheets

  • The date you received the notice

  • Any decisions only you can make, such as accepting a design change the reviewer's comment requires

  • Documents you may need to supply, such as a survey, HOA approval or product information

  • Changes you were already considering, so they can be reviewed together instead of in a separate revision later


How HB Design & Engineering Can Help

HB Design & Engineering coordinates permit plans and comment responses for residential projects across the Tampa Bay area. Structural comments are answered by the independent Florida-licensed Professional Engineers who prepare and seal the structural documents, and our team coordinates their revisions with the rest of the plan set and the resubmittal.

Learn more about our permit plans services, or see our page on permit plans in St. Petersburg.


Frequently Asked Questions


Does getting plan review comments mean my permit was denied?

No. Comments are requests for revisions or more information. Under Florida law, denial can follow if a written deficiency notice isn't answered with revisions within 10 business days, so respond promptly.


How long do I have to respond to permit comments in Florida?

Under s. 553.792, F.S., a written notice explaining why an application fails to meet the code must state that the applicant has 10 business days to submit revisions. Check your notice for the date and any local instructions.


Can I talk to the plan reviewer?

Many building departments allow applicants or their design professionals to contact reviewers with questions. Procedures vary, so check your department's website or ask the permit counter.


Will I pay again to resubmit?

It depends on the jurisdiction and the type of revision. Some charge revision fees, especially for changes after approval. Check your building department's fee schedule.


What if I disagree with a comment?

Have your design team contact the reviewer and cite the code section involved. If the disagreement isn't resolved, ask the building department about its appeal process.